§ 109-357. Final inspection and as-built plans.  


Latest version.
  • Upon completion of a project, and before a certificate of occupancy shall be granted, the applicant is responsible for certifying that the completed project is in accordance with the approved stormwater management plan. All applicants are required to submit actual as-built plans for any stormwater management facilities or practices after final construction is completed. The plan must show the final design specifications for all stormwater management facilities and practices and must be certified by a professional engineer. A final inspection by the Community Development Department is required before the release of any performance securities can occur.

(Ord. No. 16-2006, § 102-271, 11-6-2006)